March,
2008 |
• |
Reception
of laboratory results for fall 2007 drilling campaign. Viv Stuart-Williams
completes updated NI 43-101 report on U.U.P. Planning of spring
and summer 2008 exploration programs on U.U.P.,
K.U.P.
and Wakeham Basin concessions |
April
- May, 2008 |
• |
Prioritizing
of key uranium exploration targets on U.U.P.,
K.U.P.
and Wakeham Basin
following reception of Geoff Campbell geophysical interpretation
reports. |
May
- June, 2008 |
• |
U.U.P.,
K.U.P.
and Wakeham Basin
field exploration work begins, geological team prospect target
areas identified by Geoff Campbell. |
June
- September, 2008 |
• |
Beginning
of second helicopter supported diamond drilling program on U.U.P.
Goal to complete a minimum of 5,000 metres in order to determine
and delineate resource potential. |
August
- October, 2008 |
• |
Reception
of laboratories results, compilation of data, and table top
studies. |
Octobe
- December, 2008 |
• |
Beginning
of diamond drilling program on Wakeham
Basin. Goal to complete a minimum of 2,500 metres
in order to determine the resource potential. |
|